January 2007
Appointed by Merebis to provide Project Management, Cost Consultancy and
Planning Supervision services for the Fit Out of part 2nd Floor 7 Savile Row, London - 3045 sq ft.
January 2007
Appointed by Mapeley to provide Project Management, Cost Consultancy, and
Planning Supervision services for the Fit-Out of 3rd Floor West at 3 More
London.
January 2007
Appointed by ABN Amro Bank UK Property Services for annual term contract to
provide Corporate Facilities Support Role at ABN Amro Bank managing
multiple projects within UK Real Estate of 500,000 square feet. Individual
Project budget range from £100,000 to £2m.
December 2006
Appointed by ABN Amro Bank to provide Project Management, Cost Consulting
for 1st Floor Fit-out at 82 Bishopsgate, with an approximate construction
budget of £350k.
October 2006
Appointed by Abn Amro Bank to provide Project Management for 20,000 sq ft strip out of Dashwood House, Old Broad Street, London, as lease was being surrendered.
September 2006
Appointed by Abn Amro Bank to provide Project Management, Cost Consulting
for 4th Floor Fit-out at 82 Bishopsgate, construction budget £250k.
July 2006
Appointed by ABN Amro Bank Private Equity to Fit Out 1st floor Carey Lane
and relocate the business from existing premises.
June 2006
Appointed by Macintyre Hudson to provide Project Management, Cost
Consultancy, Planning Supervision and Move Management for Fit-out of
12,000sq/ft at 30-34 New Bridge Street. Relocation of 100 staff from
existing premises to new corporate headquarters building with a
construction budget of £350k.
April 2006
Appointed by ABN Amro Bank Private Clients to provide Project Management
and Cost Consultancy for Fit-out of first floor of Norfolk House, St
James's Square and subsequent relocation of 100 staff from existing
premises with a construction budget of £1.33m.
January 2006
Appointed by ABN Amro Bank UK Property Services for annual term contract to
provide Corporate Facilities Support Role at ABN Amro Bank managing
multiple projects within UK Real Estate of 500,000 square feet. Individual
Project budget range from £100,000 to £2m.
December 2005
Appointed by Abn Amro Bank Asset Management to provide Project Management
and Cost Consultancy, and Planning Supervision for 7th floor Fit-Out
project at 82 Bishopsgate with a construction budget of £160,000.
January 2005
Appointed for 12 months Corporate Facilities Support Role at ABN Amro Bank
January 2005
Appointed as Project Manager for Cutlers Gardens, Houndsditch, London 50,000sq ft Fit Out for ABN Amro Bank
December 2004
Appointed to assist ABN Amro Bank to Project Manage 82 Bishopsgate, London Reception Fit-Out
June 2004
Start Fit -Out of 20,000 sq ft floor at 6 Broadgate for Lehman Brothers - completion December 2004
January 2004
Start at 25 Bank Street Canary Wharf snagging 675,000sq ft 31 storey tower for Lehman Brothers completion june 2004 May 2004 Start Fit Out of 20,000sq ft floor at 1 Broadgate for Lehman Bothers - completion October 2004
November 2003
Start providing Snagging resource at 25 Bank Street to commence snagging of 31 storey tower in Canary Wharf - completion December
September 2003
Start PM role at Lehman Brothers stripping out 40,000 sq ft floor at 1 Broadgate - completion December 2003
2002